PLAN A
Wednesday 02/06 (08:00 - 08:30)
Recabling of the PFW for 5 current operation
Beam conditions: no beam in PS
Participants: J.P. Burnet, O. Michels, R. Steerenberg
Contact Person: R. Steerenberg
Wednesday 02/06 (08:30 - 10:00)
Setting-up of the MDSPS beam with 5 current operation of the PFW
Beam conditions: MDSPS
Participants: R. Steerenberg
Contact Person: R. Steerenberg
Wednesday 02/06 (10:00 - 15:30)
Five Current Working Point Control
Beam conditions: MD2 in PS
Participants: J.P. Burnet, M. Giovannozzi, M. Martini, E. Métral, G. Métral, O. Michels, R. Steerenberg, B. Vandorpe
Contact Person: R. Steerenberg
RF Setting-up of the 75 ns LHC beam
Beam conditions: MDSPS
Participants: R. Garoby, S. Hancock, J.-L. Vallet
Contact Person: S. Hancock
Wednesday 02/06 (15:30 - 16:00)
Recabling of the PFW for 3 current operation
Beam conditions: no beam in PS
Participants: J.P. Burnet, O. Michels, R. Steerenberg
Contact Person: R. Steerenberg
PLAN B
Adiabatic capture of particle in stable islands of transverse phase space
Beam conditions: MD2 in PS
Participants: M. Giovannozzi, M. Martini, E. Métral, R. Steerenberg.
Contact Person: M. Giovannozzi
RF Setting-up of the 75 ns LHC beam
Beam conditions: MDSPS
Participants: R. Garoby, S. Hancock, J.-L. Vallet
Contact Person: S. Hancock
In the PSB (in parallel)
Setting-up of the beams for SPS scrubbing run and MDs
No beam for the SPS during this time.
Author: Gianluigi
Arduini - AB/ABP
Last update: Friday, May 28, 2004 11:33:17 AM
Copyright
CERN