Week 23 - PS Dedicated MD - Preliminary

 

PLAN A

Wednesday 02/06 (08:00 - 08:30)

Recabling of the PFW for 5 current operation

Beam conditions: no beam in PS

Participants: J.P. Burnet,  O. Michels, R. Steerenberg

Contact Person: R. Steerenberg

 

Wednesday 02/06 (08:30 - 10:00)

Setting-up of the MDSPS beam with 5 current operation of the PFW

Beam conditions: MDSPS

Participants: R. Steerenberg

Contact Person: R. Steerenberg

 

Wednesday 02/06 (10:00 - 15:30) 

Five Current Working Point Control

Beam conditions: MD2 in PS

Participants: J.P. Burnet, M. Giovannozzi, M. Martini, E. Métral, G. Métral, O. Michels, R. Steerenberg, B. Vandorpe

Contact Person: R. Steerenberg

 

RF Setting-up of the 75 ns LHC beam

Beam conditions: MDSPS

Participants: R. Garoby, S. Hancock, J.-L. Vallet

Contact Person: S. Hancock

 

Wednesday 02/06 (15:30 - 16:00) 

Recabling of the PFW for 3 current operation

Beam conditions: no beam in PS

Participants: J.P. Burnet,  O. Michels, R. Steerenberg

Contact Person: R. Steerenberg

 

PLAN B

Adiabatic capture of particle in stable islands of transverse phase space

Beam conditions: MD2 in PS

Participants: M. Giovannozzi, M. Martini, E. Métral, R. Steerenberg.

Contact Person: M. Giovannozzi

 

RF Setting-up of the 75 ns LHC beam

Beam conditions: MDSPS

Participants: R. Garoby, S. Hancock, J.-L. Vallet

Contact Person: S. Hancock

 

In the PSB (in parallel)

Setting-up of the beams for SPS scrubbing run and MDs

 

No beam for the SPS during this time.

 