Reminder 1: There should always be 1 cycle reserved for parallel studies in the PSB.
Monday 03/08 (08:00 - 18:00) - Approaching the SPS working point close to the 1/2 or integer resonances
Beam conditions: SPS cycle = LHCFAST2, PS user = TSTLHC25 (12 bunches) and PSB user = LHCINDIV and then LHC25A (1 ring)
Nb ~ 1E10 p/b
Contact Person: J. Wenninger
Wednesday 05/07 and Friday 07/07 (08:00 - 18:00) - Bunch shape measurements for the Beam Quality Monitor (BQM)
Beam conditions
: SPS cycle = LHCFAST2, PS user = TSTLHC25 and PSB user = LHC25AIn the SPS 1 batch (12 to 48 bunches at different intensities). In the PSB 1 to 4 rings
Nb ~ 1-10E10 p/b
Contact Person: G. Papotti
Author: Elias Métral - AB/ABP