Week 44 - Parallel MD

 

Reminder 1: There should always be 1 cycle reserved for parallel studies in the PSB and PS.

Reminder 2: Continue the detailed campaign of measurements of transverse beam profiles in the SPS with all the BWS available (416, 519, 521 and 414V).

 

Monday 26/10 (09:00 - 12:00 and 14:00 - 17:00) - Validation tests of YASP on high energy orbit corrections in PS with beam

Beam conditions: PS user = 2 BP LHC-type cycle (such as TSTPS)

Contact Person: M. Gourber-Pace

 

Thursday 29/10 (08:00 - 18:00) - Generation of LHC beams in the PS without switching the beam control

Beam conditions: PS user = 2 BP cycle such as TSTLHC25 and PSB = LHC25A

Comment: This MD is incompatible with any other LHC-type multi-bunch beam (no problem with single-bunch LHC users)

Contact Person: H. Damerau

 

Friday 30/10 (08:00 - 18:00) - Rebucketing instead of LHC fine synchro in the PS

Beam conditions: PS user = LHC25 and PSB user = LHC25A&B

Comment: No other LHC-type beam (multi/single bunch) from the PS is possible in parallel to this MD

Contact Person: H. Damerau

 

 


Author: Elias Métral - AB/ABP