Week 45 - Parallel MD
Reminder 1: There should always be 1 cycle reserved for parallel studies in the PSB and PS.
Reminder 2: Continue the detailed campaign of measurements of transverse beam profiles in the SPS with all the BWS available (416, 519, 521 and 414V).
Monday 02/11 (08:00 - 18:00) -
Check in the PS the 25 / 50 / 75 ns variants to be ready for the Long Injector MD of following day + Ecloud studies in the PS with LHC 25 nsContact Person: H. Damerau + Silke Federmann
Tuesday 03/11 (08:00) to Thursday 05/11 (08:00)
Injector Long MD
Tuesday 03/11 (08:30 - 16:30) -
Validation of YASP on new TT2 SEMs front-ends HW and SWBeam conditions: PS user = MDPRO-like cycle (1 BP). MDPRO will be used with different settings to validate the steering with various extraction schemes (Fast and CT).
Contact Person: M. Gourber-Pace
Wednesday 04/11 (08:30 - 16:30) -
Validation of YASP on new TT2 SEMs front-ends HW and SWBeam conditions: PS user = MDPRO-like cycle (1 BP). MDPRO will be used with different settings to validate the steering with various extraction schemes (Fast and CT).
Contact Person: M. Gourber-Pace