Week 38 - Floating Injector MD
(From Thursday 23/09 at 08:00 to Friday 24/09 at 00:00 in // to LHC, total duration 16 hours)
The starting time of this MD as well as the actual number of MD hours depend on the beam request and filling of LHC
- Thursday 08:00 - Thursday 18:00 => Tests with the 4 injection I-LHC cycle (16.8 s)
Beam conditions: 4 early ion bunches injected into the SPS
- LEIR user = EARLY
- PS user = LHCION
- SPS user = LHCION2
- RF MMI target = LHCION
Contact people: T. Bohl, P. Baudrenghien, D. Manglunki
- Thursday 18:00 - Thursday 19:00 => Set up of the supercycle coastable at either 55 or 270 GeV/c. The cycle name is MD_25.92_55_270_2009_V1
Beam conditions: 12 bunches of LHC 25ns beam at half intensity (5e10 ppb)
- PSB user = LHC25A (Ring 3, half intensity archive)
- PS user = LHC25
- SPS user = LHCMD1 (in pulsed mode), COAST1 (in coasting mode)
- RF MMI target = LHC25NS
- Timing sequence = LHCMD2 0/1/2 (Coastable 55-270 GeV)
Contact people: BE/OP, BE/RF
- Thursday 19:00 - Friday 00:00 => SPS studies in view of an installation of a KEK-B crab cavity in the SPS
Beam conditions: as above
- PSB user = LHC25A (Ring 3, half intensity archive)
- PS user = LHC25
- SPS user = LHCMD1 (in pulsed mode), COAST1 (in coasting mode)
- RF MMI target = LHC25NS
- Timing sequence = LHCMD2 0/1/2 (Coastable 55-270 GeV)
Contact people: E. Métral, R. Calaga, F. Zimmermann
- Friday 00:00 - Friday 01:00 => Recovery from MD, switch back to physics
- Change of supercycle
- Send beam to physics at the earliest time after set up of the physics beams
Contact people: BE/OP
Author:
Giovanni Rumolo - BE/ABP
Last update: Tuesday, September 7, 2010 17:17:22 AM