Week 35 - Long dedicated SPS MD
Monday 29/08/2011 and Friday 02/09/2011 during LHC stop


Monday 08h00 - 16h00

Supercycle: fully dedicated MD (26 bp)

MD title:
Set up of the multi-bunch (up to 48) injection on 270 GeV/c coastable cyle + coastable Q20 cycle at 270 GeV/c
Beam conditions: train with up to 48 bunches of 25ns beam for set up with coastable at 270 GeV/c + single bunch with nominal intensity for set up with Q20 coastable at 270 GeV/c
Cycle:
MD_25.92_55_270_2009_V1 (26bp), MD_25.92_55_270_Q20_2009_V1 (26bp)

PSB user =   LHC_A, LHCINDIV
PS user = MD6, LHCINDIV
SPS user = LHCMD2 (pulsed), COAST2 (coast)
RF MMI target = MD1

Contact People: S. Cettour-Cave, T. Bohl, BE/OP, BE/RF

Additional remarks: 

 

Monday 16h00 - 21h00

Supercycle: fully dedicated MD (26bp)

MD title:
Emittance growth in coast for crab cavity studies
Beam conditions: single bunch with variable intensity (1e10 to 1.2e11) to be coasted at 270 GeV/c on Q20 optics
Cycle:
MD_25.92_55_270_Q20_2009_V1 (26bp)


PSB user =   LHCINDIV
PS user = LHCINDIV
SPS user = LHCMD2 (pulsed), COAST2 (coast)
RF MMI target = MD1

Contact People: R. Calaga, E. Métral, R. Tomás, F. Zimmermann

Additional remarks: 

 

Monday 21h00 - 22h00

Supercycle: SFTPRO-like cycle + two (or more) CNGS without beam

MD title:
Switch to the new supercycle with the MD version of SFTPRO
Beam conditions: low intensity SFTPRO-like beam (1 to 2e12 p), only one batch injection into the SPS
Cycle: SFT_LONG_L9690_2010_MD_V1

Contact People: BE/OP, BE/RF

Additional remarks: no RF gymnastics before the extraction. Voltage before extraction should be reduced as well to minimize the Dp/p during extraction and get max resolution for following dispersion measurement.

 

Monday 22h00 - Tuesday 05h00

Supercycle: SFTPRO-like cycle + two (or more) CNGS without beam

MD title:
TT20 steering tests and validation of simulations
Beam conditions: low intensity SFTPRO-like beam (1 to 2e12 p), only one batch injection into the SPS
Cycle: SFT_LONG_L9690_2010_MD_V1


PSB cycle = SFTPRO-MD-SPS_PSB (low intensity SFTPRO)
PSB timing user = MD4
PS cycle = SFTPRO_CT_150E10
PS timing user = MD3

SPS user =
SFTLONG1
RF MMI target = SFT-CT

Contact Person: O. Berrig, D. Manglunki, S. Massot

Additional remarks:

 

Tuesday 05h00 - Thursday 08h00

Cool down + INJECTOR TECHNICAL STOP

 

Thursday 08h00 - Friday 08h00

Dedicated physics run: UA9
Beam conditions: nominal single LHC-type bunch
Cycle:
MD_25.92_55_270_2009_V1 (26bp)

PSB user =   LHCINDIV
PS user = LHCINDIV
SPS user = LHCMD2 (pulsed), COAST2 (coast)
RF MMI target = MD1

 
Contact Person
: W. Scandale

Additional remarks: 

 

Thursday 06h00 - Thursday 14h00 + Friday 12h00 - Friday 22h00

PS MD title: Tests for a slow extraction of protons at 2.12 GeV/c from the PS to the East Area
Beam conditions: EAST-type beam
Cycle:

PSB user =   EASTA
PS user = EASTA
SPS user =
RF MMI target =

 
Contact Person
: O. Hans, S. Gilardoni, R. Steerenberg

Additional remarks: Beam to the East area will have to be stopped during this MD, because special settings of the extraction elements are required, which are not PPM

 

Friday 08h00 - 19h00

Supercycle: total 36bp, made of two long flat bottom LHC cycles, one nominal optics and the other one low gamma transition

MD title:
 Optimization of the 25ns beam on nominal optics and Q20
and electron cloud measurements
Beam conditions: up to 4 batches of nominal 25ns LHC beam (1.2e11 ppb)
Cycle:
LHCMD_25ns_2011_V1 (18bp) + LHCMD_25ns_Q20_2011_V1 (18bp)

PSB user = LHC_A + LHC_B, LHC_SU_A + MD4
PS cycle = MD6
SPS user = LHCMD1, LHCFAST3
RF MMI target = LHCMD3, MD2

 
Contact People
: SPSU team

Additional remarks: 

 

Friday 14:00 - 16:00

MD title: BLM tests in the dump line
Beam conditions: low intensity beam (between 1e9 and 1e10 p)
Cycle:

PSB user = copy of LHCPROBE to an MD user
PS cycle =
PS timing user =
SPS user =
RF MMI target =

 
Contact People
: Eduardo Nebot Del Busto, Bernd Dehning

Additional remarks: This MD will be carried out in parallel with the SPS users (see next) and PS (and PSB? compatibility to be checked) physics users. During these tests it has be made sure that only this beam goes to the beam dump, therefore the other users must have either PS (or ISOLDE?) as destination and have zero cycles in spare.

 

Friday 19h00 - 20h00

Change of supercycle from LHCMD_25ns_2011_V1 (18bp) + LHCMD_25ns_Q20_2011_V1 (18bp) to MD_25.92_55_270_2009_V1 (26bp)

Contact People: BE/OP, BE/RF

 
Friday
20:00 - Saturday 07:00

Supercycle: fully dedicated MD (26bp)

MD title:
Collimator studies + vacuum degassing measurements of jaws movements
Beam conditions: single bunch on coastable at 270 GeV/c
Cycle:
MD_25.92_55_270_2009_V1 (26bp)

PSB user =   LHCINDIV/LHCINDIV
PS user = LHCINDIV/LHCINDIV
SPS user = LHCMD2 (pulsed), COAST2 (coast)
RF MMI target = MD1

Contact People: D. Wollman, G. Bregliozzi, et al.

Additional remarks: 

 

Saturday 07h00 - Saturday 08h00

Recovery from MD and switch back to physics

 

Back to the Injector MD home page

Back to the Long MD page


Author: Giovanni Rumolo BE-ABP-ICE
Last update: Friday, September 02, 2011 08:41:13 AM