Monday 21/5/2012 to Friday 25/5/2012, between 08h00 and 18h00 compatibly with physics and LHC

SPS MDs

Monday 21/05

MD title: Preparations for measuring resonance driving terms in Q20 optics
Beam conditions: Probe LHC-type beam

PSB user = LHCPROBE
PS user = LHCPROBE
SPS user = MD1
RF MMI target = MD1

Contact People: H. Bartosik

Additional remarks:

 

MD title: Preparation of extraction from the Q20 optics
Beam conditions: Probe LHC-type beam

PSB user = LHCPROBE
PS user = LHCPROBE
SPS user = LHC2
RF MMI target = MD3

Contact People: H. Bartosik

Additional remarks: takes place when LHC is ramping down or not having beam, beam sent down tothe TEDs

 

Thursday 24/05 - Friday 25/05

MD title: Preparation of extraction from the Q20 optics
Beam conditions: Probe LHC-type beam

PSB user = LHCPROBE
PS user = LHCPROBE
SPS user = LHC2
RF MMI target = MD3

Contact People: H. Bartosik

Additional remarks: takes place when LHC is ramping down or not having beam, beam sent down tothe TEDs

 

 

PS MDs

MDus1

MD title: Measurement of the resonance driving terms
Beam conditions: LHCINDIV-type beam at nominal intensity


PSB user = LHCINDIV or LHCPROBE
PS user = LIU_1BP_PSB-LHC_INDIV 

Contact People: R. Wasef, F. Schmidt

Additional remarks:

 

MDus2

MD title: MTE hybrid tests
Beam conditions: LHC-type beam


PSB user = LHCINDIV or LHCPROBE
PS user = MTE_2bp_Cedric

Contact People: C. Hernalsteens

Additional remarks:

 

MDus3

MD title: MTE Beam Stability (new version)
Beam conditions: LHC single bunch-type beam


PSB user = LHCINDIV or LHCPROBE
PS user = MTE_2bp_Antoine

Contact People: A. Lachaize

Additional remarks:

 

MDus4

MD title: Tuning of working point from injection in 5 CM
Beam conditions: EASTC-type beam


PSB user = EASTC_ForPSMatrixMeas_PSB
PS user = LIU_V1MatrixMeas

Contact People: A. Huschauer, BE/OP

Additional remarks:

 

MDus4bis

MD title: Tune diagram measurements
Beam conditions: large emittance beam


PSB user = XL_T_EMITT_PSB
PS user = LIU_V1_Tune_Alex

Contact People: A. Huschauer, BE/OP

Additional remarks: Measurements can be done or continued at night time, when possible

 

 MDus5

MD title: Electron cloud + transverse instabilities @ flat top
Beam conditions: LHC-type beam


PSB user = LHC_MD_A + LHC_MD_B
PS user = LHC_25_FT_instab

Contact People: M. Pivi, G. Iadarola

Additional remarks:

 

  MONDAY
(21/05)
TUESDAY**
(22/05)
WEDNESDAY
(23/05)
THURSDAY
(24/05)
FRIDAY
(25/05)
Morning
8:00 - 14:00
MDus3
MDus5
MDus1
MDus3
MDus5
MDus4
MDus2
MDus1
MDus4
MDus1
MDus4bis
Afternoon
14:00 - 20:00
MDus5
MDus3
MDus3
MDus4
MDus2
MDus4
MDus3
MDus2
MDus4bis
MDus1
Night
20:00 - 8:00
MDus5 MDus1
MDus3
MDus2 MDus3 MDusNO

MDusx is the MD user with priority
MDusx is the MD user in "spare" (i.e. replacing MDusx when not available, or called in when second MD cycle available)
** Tuesday 22/05 is a day of floating Injector MD, in which MDs have priority on physics in all injectors

 

PSB MDs

Monday 21/05 to Friday 25/05


MD title: Test of the new Finemet cavities in Ring 4
Beam conditions: only Ring 4


PSB user = FINEMET_TEST

Contact People: M.E. Angoletta, M. Paoluzzi

Additional remarks:

 

Tuesday 22/05

MD title: Emittance growth measurements on 160 MeV flat cycle
Beam conditions: only Ring 2


PSB user = 160MEV_Flat-Cycle

Contact People: E. Benedetto, V. Forte, A. Molodozhentsev

Additional remarks: The transverse emittance measurements will be done at flat top and for different bunch lengths (controlled through the C02 + C04 voltages and phase between cavities) 

 