Week 23 - Parallel MD
During the week the PSB will continue to prepare the beams for the PS MDs,
the cycle for LHC low intensity and the cycle for impedance measurements in the
SPS (which should take place during the week 25, i.e. week after the scrubbing
run). The PS will continue to work on the MTE cycle (MD2) and on the
high-intensity cycle for CNGS (MD3).
Monday 02/06 (08:00 - 18:00) - Test of the LHC beta-beating application in the SPS
Beam conditions: SPS user = LHCFAST1 (SPS supercycle = SFT-CNGS-LHCFAST2_V2), PS user = LHC25 and PSB user = LHC25A
#bunches = 12 (1 PSB ring)
Low intensity per bunch (~ 1E10 p/b)
Contact Person: R. Tomas
Tuesday 03/06 (08:00 - 18:00) - Controlled transverse emittance blow-up in the SPS
Beam conditions: SPS user = LHCFAST1 (SPS supercycle = SFT-CNGS-LHCFAST2_V2), PS user = LHC25 and PSB user = LHC25A & B
#bunches = 12
Low intensity per bunch (~ 1E10 p/b)
Contact Person: D. Manglunki
Wednesday 04/06 (08:00 - 18:00) - Setting-up of the transverse dampers in the SPS
Beam conditions: SPS user = LHCFAST1 (SPS supercycle = SFT-CNGS-LHCFAST2_V2), PS user = LHC25 and PSB user = LHC25A & B
#bunches = 12-48
Intensity: Any
Contact Person: W. Hofle
Thursday 05/06 (08:00 - 18:00) and Friday 06/06 (08:00 - 18:00) - Final setting-up of the feedforwards in the SPS and of the TWC 800 MHz in view of the scrubbing run
Beam conditions: SPS user = LHCFAST1 (SPS supercycle = SFT-CNGS-LHCFAST2_V2), PS user = LHC25 and PSB user = LHC25A & B
#bunches = 72
Intensity: Nominal
Contact Person: T. Bohl
Author: Elias Métral - AB/ABP
Last update:
Monday, June 02, 2008 04:01:44 PM
Copyright
CERN