Week 24 - Parallel MD

During the week the PSB will continue to prepare the beams for the PS MDs, the cycle for LHC low intensity and the cycle for impedance measurements in the SPS (which should take place during the week 25, i.e. week after the scrubbing run). The PS will continue to work on the MTE cycle (MD2) and on the high-intensity cycle for CNGS (MD3).
 

Monday 09/06 (16:00) until Thursday 12/06 (09:00)

SPS scrubbing run

 

Thursday 12/06 (09:00 - 15:00) - Study of the radiation levels on top of the TDC2 tunnel in the North Area vs losses at the TT20 splitters => Confirmed by the Physics coordinator on 05/06/08 (beam back to physics at 15:00)

This MD will be done during the necessary re-steering of the TT20 line before sending the beam back to physics (i.e. it is not a special beam: it is the beam for physics)

Beam conditions: SPS user = SFTPRO1 (SPS supercycle = SFT-CNGS-LHCFAST2_V2)

Contact Person: H. Vincke

 

Friday 13/06 (08:00 - 18:00) - Check the LHCPILOT and LHCINDIV beams in the PS (to be ready for the TI2 tests of the coming week-end)

 


Author: Elias Métral - AB/ABP
Last update: Wednesday, June 11, 2008 02:33:36 PM