Week 33 - Parallel MD

Reminder 1: There should always be 1 cycle reserved for parallel studies in the PSB.

Reminder 2: During the week (when possible) the PS will continue to work on the Matrix measurements with the 5-CM PFWs.

 

Monday 11/08 (16:00) to Thursday 14/08 (08:00)

Injector Long MD

 

Thursday 14/08 and Friday 15/08 (08:00 - 18:00) - Prepare, in the PSB and in the PS, the beams which will be used for the LHC injection tests of week-end 23-24/08/08

Beams which will/could be used:

1) LHCPROBE with the new definition (following the first LHC injection tests of week-end 09-10/08/08): 2E9 p/b (instead of 5E9 p/b)

2) LHCPROBE with the new definition (2E9 p/b) composed of 2 bunches spaced by 525 ns (as for TOTEM)

3) LHCPILOT

 


Author: Elias Métral - AB/ABP
Last update: Wednesday, August 13, 2008 01:58:07 PM