Week 39 - Parallel MD

 

Reminder 1: There should always be 1 cycle reserved for parallel studies in the PSB.

Reminder 2: During the week (when possible) the PS will continue to work on the production of LHC50 in 1 batch to be ready for the Long Injector MD of week 41.

 

Monday 21/09 (08:00 - 18:00) - SPS ion commissioning (setting-up in // of the early ion beam)

Beam conditions: SPS cycle = SFTLONG1 + 4 CNGS1 + LHCION1, PS user = LHCION (MDION is reserved for the nominal beam) and LEIR user = EARLY

SPS user Timing = LHCION1 (LHCION2 is reserved for the dedicated MD)

Contact Person: D. Manglunki

 

Tuesday 22/09 (08:00) to Wednesday 23/09 (16:00)

Injector Long MD

 

Thursday 24/09 (08:00 - 18:00) and Friday 25/09 (08:00 - 18:00) - Check LHC beams which will be required for the TI2&8 tests of the week-end (on LHCFAST2) => p & ions

Thursday will be devoted to the ions and Friday to the protons

Contact Person: OP

 


Author: Elias Métral - AB/ABP
Last update: Friday, September 18, 2009 12:21:17 PM
Copyright CERN