Week 37 - Parallel MD (Monday through Friday 13-17/09/2010, from 8h00 to 18h00)

N.B. The parallel MDs take place all the time from 8:00 to 18:00, provided the LHC is in store or does not request beam. The MD cycle is removed from the supercycle during the LHC filling

 

Monday  - Optics studies for the change of gamma-transition

Beam conditions and cycle Single LHC-type bunch on MD_26_L7200_Q20_V1

PSB user =   LHCINDIV

PS user = LHCINDIV

SPS user = MD1

RF MMI target = LHCMONO

Sequence = PSB.LHCINDIV.1_0->CPS.LHCINDIV.2_1->SPS.MD1.6_2

Contact PersonY. Papaphilippou, H. Bartosik

 

Tuesday - Verification of fine synchronization for pattern detection on different LHC cycles with the SPS BQM

Beam conditions and cycle Different types of LHC beams (single bunch, bunch trains, multibunch-injections) on different types of cycle

PSB user =   LHCINDIV, LHCPROBE, LHCPILOT

PS user = LHCINDIV, LHCPROBE, LHC75

SPS user = LHCFAST1, LHCFAST3, LHC3, LHC2, LHCFAST2

RF MMI target = LHCMONO, LHC25NS

Contact PersonG. Papotti

 

Tuesday - Measurement of cavity return phases 10/20/40 MHz 

Beam conditions: 50ns LHC-type beam with variable intensities

PSB user = LHC50

PS user = LHC50

SPS user =

RF MMI target =

Contact Person: H. Damerau

 

The following MDs can take place at the PS when there's enough space for the needed cycle both in the PSB and in the PS (ask the machine supervisors)

Monday - Friday  - TMCI at transition in the PS

Beam conditionsTOF-like beam

PSB user = TSTPS

PS user = MD3

SPS user =

RF MMI target =

Contact PersonT. Bohl, P. Baudrenghien, D. Manglunki

 

Wednesday - Friday  - Studies with ions on a // 1 injection cycle

Beam conditions: early ion beam

LEIR user = EARLY

PS user = LHCION

SPS user = LHCION1

RF MMI target = LHCION

Contact PersonT. Bohl, P. Baudrenghien, D. Manglunki

 


 

Author: Giovanni Rumolo BE/ABP-ICE
Last update: Tuesday September 7, 2010 16:59:25 PM
Copyright CERN