Week 20 - Parallel MD
Monday 16/5/2011 to Friday 20/5/2011, between 08h00 and 18h00 compatibly with physics and LHC

SPS MDs

Monday 16/05 - Wednesday 18/05

MD title: Working point scan and emittance evolution studies on a Q20 flat cycle. Comparison with a Q26 cycle
Beam conditions: single bunch with intensity per bunch up to 3.5e11 on MD_26_L7200_Q20_V1 or MD_26_L7200_V1 cycle


PSB user = MD4
PS timing user = LHCINDIV
PS cycle = LHCINDIV
SPS user = MD1
RF MMI target = MD1

Contact People: H. Bartosik, Y. Papaphilippou, B. Salvant, BE/OP, BE/RF

Additional remarks: transverse emittance measurements along the cycle in the PS are performed in parallel by E. Benedetto

Wednesday 18/05

MD title: Longitudinal instabilities at flat top with radial steering
Beam conditions: two bunches, first nominal and second with variable intensity on LHC_INDIV_2011_V1


PSB user = LHCINDIV + LHCPROBE, LHCINDIV x2, LHCINDIV + MD4
PS timing user = LHCINDIV
PS cycle = LHCINDIV
SPS user = LHC4
RF MMI target = LHCMONO

Contact People: T. Bohl

Additional remarks: the intensity of the second bunch is changed by changing the PSB user (LHCPROBE for a second bunch with very little intensity and MD4 to scan the range between LHCPROBE and nominal LHCINDIV)

 

Thursday 19/05

MD title: Transverse emittance measurements with 4 batches of 25ns beam
Beam conditions: 4 batches of 25ns beam with nominal intensity per bunch (1.2e11)
Cycle:
LHCMD_25ns_2011_V1, 18bp


PSB user =   LHC_MD_A + LHC_MD_B
PS cycle = LHC25
PS timing user = MD6
SPS user = LHCMD1
RF MMI target = LHCMD3

Contact People: G. Rumolo, et al.

Additional remarks: simultaneous transverse emittance measurements in the PSB and PS are desirable

Friday 20/05

MD title: Working point scan and emittance evolution studies on a Q20 flat cycle. Comparison with a Q26 cycle
Beam conditions: single bunch with intensity per bunch up to 3.5e11 on MD_26_L7200_Q20_V1 or MD_26_L7200_V1 cycle


PSB user = MD4
PS timing user = LHCINDIV
PS cycle = LHCINDIV
SPS user = MD1
RF MMI target = MD1

Contact People: H. Bartosik, Y. Papaphilippou, B. Salvant, BE/OP, BE/RF

Additional remarks: transverse emittance measurements along the cycle in the PS are performed in parallel by E. Benedetto

 

PS MDs

Monday 16/05 to Friday 20/05

MD title: Injection of 8 x PSB bunches into h=9 (joint with PSB)
Beam conditions: 50ns type beam, but with 4 Booster rings and with final bunch spacing adjusted to h=9 in the PS (and not h=7, like the present LHC beams)


PSB user =   MD3
PS timing user = MD9
PS cycle = LIU_V1

Contact People: A. Findlay, H. Damerau, S. Hancock

Additional remarks:

 

MD title: Working point optimization
Beam conditions:


PSB user = LHC_A or LHC_B
PS timing user = MD9
PS cycle = LIU_V1

Contact People: E. Benedetto, G. Métral, S. Gilardoni

Additional remarks:

 

MD title: Tests of magnetic elements (includes low energy correctors, DHZ15-60 at injection, low energy quadrupoles and skew quadrupoles at 2 GeV)
Beam conditions:


PSB user = LHC_A or LHC_B
PS timing user = MD9
PS cycle = LIU_V1

Contact People: G. Métral, S. Gilardoni

Additional remarks:

 

PSB MDs

Monday 16/05 to Friday 20/05

MD title: Set up of 8 x PSB bunches to fit into PS h=9 (joint with PS)
Beam conditions: 50ns type beam, but with 4 Booster rings and with final bunch spacing adjusted to h=9 in the PS (and not h=7, like the present LHC beams)


PSB user =   MD3

Contact People: BE/OP

Additional remarks:

Back to the Injector MD home page

Back to the Parallel MD page


Author: Giovanni Rumolo BE-ABP-ICE
Last update: Wednesday, May 18, 2011 07:04:06 PM