Week 39 -
Floating SPS MD
Wednesday 26/09/2012 in parallel with LHC
operation
Consigne for SPS MDs
Put this virtual event from CBCM Timing new table in
enabled on one cycle in the sequence.
SX.EA-SACQ-CTM (Exp Area-Start
Acq) (200 ms)
SX.EA-EACQ-CTM (Exp Area-End Acq ) (4400 ms)
Wednesday 07h00 - Wednesday 17h00
Supercycle:
2 x
CNGS + LHCMD_50ns_D_Q20_2011_V1 (5bp+5bp+18bp=28bp)
MD title:
25ns LHC beam with Q20 optics
Beam conditions:
25ns LHC beam
Cycle:
LHCMD_50ns_D_Q20_2011_V1 (18bp)
PSB user = LHC_MD_A + LHC_MD_B (LHC25_DB_A + B)
PS user = MD6 (LHC25)
SPS user =
LHC2
RF MMI target = LHCMD5
Contact People: H. Bartosik, Y. Papaphilippou, E. Shaposhnikova, T. Bohl, G. Iadarola, G. Rumolo
Additional remarks:
Back to the Injector MD home page
Author: Giovanni
Rumolo BE-ABP-ICE
Last update:
Wednesday, September 19, 2012 05:37:32 PM
Copyright
CERN