Week 43 - Parallel MD
Reminder 1: There should always be 1 cycle reserved for parallel studies in the PSB and PS.
Reminder 2: Continue the detailed campaign of measurements of transverse beam profiles in the SPS with all the BWS available (416, 519, 521 and 414V).
Monday 19/10 (08:00 - 18:00)
PS(&SPS) ion commissioning (setting-up in // of the early ion beam)
Beam conditions
: SPS cycle = SFTLONG1 + 4 CNGS1 + LHCION1, PS user = LHCION (MDION is reserved for the nominal beam) and LEIR user = EARLYSPS user Timing = LHCION1 (LHCION2 is reserved for the dedicated MD)
Contact Person: D. Manglunki