Week 19 - Parallel MD
Monday 9/5/2011, between 08h00 and 18h00 compatibly with SPS Long MD
Wednesday to Friday 11-13/5/2011 between 08h00 and 18h00 compatibly with physics, SPS Long MD, Technical Stop and LHC

SPS MDs

Monday 09/05 + Wednesday 11/05

Long SPS MD

 

Thursday 12/05 - Friday 13/05

MD title: to be decided
Beam conditions:


PSB user =  
PS user =
SPS user =
RF MMI target =

Contact People

Additional remarks:

 

PS MDs

Monday 09/05 + Wednesday 11/05 to Friday 13/05

(pending HW change, could be done also as parallel MD Thursday and Friday) 
MD title: Use of 2 or 3 x 80 MHz cavities for final phase space rotation (joint with SPS)
Beam conditions: 25 and 50ns beams


PSB user =   LHC_A or LHC_MD_A + LHC_MD_B
PS timing user =  MD6 or LHC
PS cycle = LHC_50 or LHC25

Contact People: H. Damerau, S. Hancock

Additional remarks:

 

MD title: Working point optimization
Beam conditions:


PSB user = LHC_A or LHC_B
PS timing user = MD9
PS cycle = LIU_V1

Contact People: E. Benedetto, G. Métral, S. Gilardoni

Additional remarks:

 

MD title: Tests of magnetic elements (includes low energy correctors, DHZ15-60 at injection, low energy quadrupoles and skew quadrupoles at 2 GeV)
Beam conditions:


PSB user = LHC_A or LHC_B
PS timing user = MD9
PS cycle = LIU_V1

Contact People: G. Métral, S. Gilardoni

Additional remarks:

 

PSB MDs

Monday 09/05 + Wednesday 11/05 to Friday 13/05

MD title: Set up of single batch transfer beam to be injected into PS h=9
Beam conditions: single batch transfer LHC beam on 4 PSB rings


PSB user =   MD2 (if available, or LHC_SU_B)

Contact People: A. Findlay

Additional remarks:

 

Back to the Injector MD home page

Back to the Parallel MD page


Author: Giovanni Rumolo BE-ABP-ICE
Last update: Monday, May 09, 2011 08:51:40 AM
Copyright CERN