2010 MD Planning



 

How to submit a request of machine development time?

 

Send a short summary of your MD to the MD Coordinator

 

Status of the MDs in 2010

 

Coupling between the different machines (to be entered in the CBCM) => More explanations

 

SPS RF MMI mapping

 

Please note that the links below are to be considered preliminary drafts until the official announcement of the schedule is sent out to all the MD users via email


 

Long MD sessions

Weeks: 17 - 22 - 29 - 35 - 42

 




FLOATING MD sessions
(LHC has priority) => duration of 10, 16 or 24 h

Weeks: 24 - 34- 38 - 40 - 43 - 44 - 45 - 46

 


 

Sessions in parallel with physics

Weeks: 16 - 17 - 18to21 - 22 - 23 - 24 - 25 - 26 - 27 - 28 - 29 - 30 - 31 - 32 - 33 - 34 - 36 - 37 - 38 - 39 - 40 - 41 - 42 - 43 - 44 - 45 - 46 - 47- 48

 


 

SPS Physics and MD cycles

- LHCFAST_L7200_2009_V2.csv (picture) => LHCFAST cycle (6 BP = 7.2 s) to have similar Eddy currents on SFTPR0 as the ones produced by CNGS. The user LHCFAST1 is reserved for the bunch LHCPROBE and the user LHCFAST2 for the LHCINDIV bunch.

- MD_MTE_400_2009_V1.csv (picture) => MD cycle for MTE (5 BP = 6 s = same length as a CNGS cycle).

- MD_26_L7200_V1.csv (picture) => MD segment at 26 GeV/c (6 BP = 7.2 s = same length as a LHCFAST cycle).

- LHC_4Inj_FB10860_FT500_2010_V1.csv (picture) => LHC 4 batches 3600 ms / batch (18 BP = 21.6 s).

- LHC_4Inj_FB7260_FT500_2010_V1.csv (picture) => LHC 4 batches 2400 ms / batch (15 BP = 18 s)

 


 

MD requirements in terms of cycles

Weeks: 19 - 20 - 21 - 22 - 23 - 24 - 25 - 26 - 27 - 28 - 29 - 30 - 31 - 32 - 33 - 34 - 35 - 36 - 37 - 38 - 39 - 40 - 41 - 42 - 43 - 44 - 45 - 46 - 47

 